New Railway Track Commissioning in Odisha Registers Over 3.5 Times Increase; 2,150 km Commissioned During 2014–25 as Against 267 km in 2009–14

PRID2239725 MinistryMinistry of Railways Released Reading4 min

226 Km of Khurda Road-Bolangir New Line Commissioned, All Seven Tunnels Excavated on Final 75-Km Daspalla-Purunakatak Section 57 Km of Salegaon-Budhapank 3rd and 4th Line Commissioned; 6 Major Bridges and 2 Stations Complete on Remaining 28 Km Posted On: 13 MAR 2026 5:43PM by PIB Delhi Railway has taken up infrastructure upgradation in Odisha in a big way. Railway Budget: Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Odisha is as under: Period Outlay 2009-14 ₹ 838 Cr./year 2025-26 ₹ 10,599 Cr. (Nearly 13 times) Track Construction: The details of commissioning/laying of new track falling fully/partly in the State of Odisha during 2009-14 and 2014-25 is as under: Period New Track Commissioned Average Commissioning of new tracks per year 2009-14 267 Km 53 Km 2014-25 2,150 Km 195 Km (More than 3.5 times) Project Sanctioned: As on 01.04.2025, 49 projects (19 New Lines and 30 Doubling), of a total length of 4,010 Km, costing ₹ 67,496 crore, falling fully/partly in Odisha, are sanctioned, out of which 1,429 km length has been commissioned and an expenditure of ₹28,043 crore has been incurred upto March’ 2025. The summary is as under:- Category No of sanctioned Projects Total Length NL/GC/DL (in Km) Length Commissioned till Mar'25 (in Km) Total Exp upto Mar'25 ( ₹ in Cr) New Lines 19 1,544 256 6,270 Doubling/Multi-tracking 30 2,466 1,173 21,773 Total 49 4,010 1,429 28,043 Recently Completed Projects: Details of some of the recently completed projects falling fully/partly in Odisha are as under: SN Name of Project Cost (In Crores of ₹) 1 Daitari-Banspani New Line and Jakhapura-Haridaspur 3 rd Line (179 Km) 1,317 2 Jharsuguda - Sardega New Line (50 Km) 1,598 3 Haridaspur-Paradeep New Line (82 Km) 2,397 4 Angul-Sukinda New Line (104 Km) 2,834 5 Champa-Jharsuguda 3 rd Line (152 Km) 1,227 6 Sambalpur-Titlagarh Doubling (182 Km) 2,262 7 Rourkela-Jharsuguda 3 rd Line (101 Km) 1,313 8 Banspani-Daitari-Tomka-Jakhapura Doubling (164 Km) 1,827 9 Sambalpur-Talcher Doubling (174 Km) 1,539 10 Raipur - Titlagarh Doubling (203 Km) 1,171 11 Jharsuguda-Sardega Doubling (50 Km) 3,200 Ongoing Projects: Further, some of the main projects falling fully/partly in Odisha which have been taken up are as under: SN Name of Project Total Cost (In Crores of ₹) 1 Junagarh-Nabarangpur New Line (116 Km) 2,865 2 Nabarangpur-JeyporeNew Line (41 Km) 748 3 Jeypore-Malkangiri New Line (130 Km) 2,344 4 Malkangiri &ndash; Pandurangapuram New Line (174 Km) 3,592 5 Buramara-Chakulia New Line (60 Km) 1,459 6 Gunupur-Therubali New Line (74 Km) 1,166 7 Puri - Konark New Line (32 Km) 492 8 Badampahar-Kendujhargarh New Line (82 Km) 1,876 9 Bangriposi-Gorumahisani New Line (86 Km) 2,269 10 Bargarh Road-Nawapara Road New Line (138 Km) 2,622 11 Vizianagram-Titlagarh 3 rd Line (265 Km) 6,996 12 Jarapada- Budhapank 3 rd & 4 th Line with flyover at Talcher (101 Km) 810 13 Budhapank- Salegaon via Rajatgarh 3 rd & 4 th Line (170 Km) 2,023 14 Nergundi - Vizianagaram 3 rd Line (385 Km) 4,963 15 Kottavalasa-Koraput Doubling (189 Km) 2,500 16 Koraput-Singapur Road Doubling (165 Km) 2,362 17 Jagdalpur-Koraput Doubling (107 Km) 1,547 18 Jharsuguda-Bilaspur 4 th line (206 Km) 2,596 19 Bondamunda-Ranchi Doubling (159 Km) 3,029 20 Narayangarh-Bhadrak 3 rd line (153 Km) 2,136 21 Bhadrak-Nergundi 3 rd Line (92 Km) 1,284 The progress of some of the major projects is as under: 1. Khurda Road-Bolangir (301 Km) new line: The latest cost of the project is ₹5,089 crore. Expenditure of ₹4,311 crore has been incurred on this project upto March, 2025. An outlay of ₹1938 crore has also been provided in the financial year 2025-26. Status of project is as under:- Khurda Road &ndash; Daspalla (106 Km) : Commissioned Daspalla &ndash; Purunakatak (75 Km) : Works have been taken up. Purunakatak &ndash; Bolangir (120 Km) : Commissioned Status of Daspalla &ndash; Purunakatak (75 km) is as under:- SN Activity Scope Status 1 Tunnel 7 nos (11.96 Km) 6 nos completed (7.7 Km).Works taken up in balance 1 tunnel 2 Important Bridge 5 All completed 3 Station Building 5 Works have been taken up 2. Construction of 3 rd and 4 th line between Salegaon- Budhapank(85 Rkm): The work has been taken up. Status is as below:- Salegaon &ndash; Rajathgarh (23 Km) : Commissioned Rajathgarh &ndash; Dhenkanal (20 Km) : Land acquisition & forest land diversion completed. 4 major bridges completed. Balance work has been taken up. Dhenkanal &ndash; Meramundali (34 Km) : Commissioned Meramundali &ndash; Budhapank (8 Km) : Land acquisition & forest land diversion completed. 2major bridges and 2 stations completed. Balance work has been taken up. Sanction of any railway project depends upon many parameters/factors which include the following: Anticipated traffic projections and Remunerativeness of the proposed route First and last mile connectivity provided by the project Connection of missing links and providing additional route Augmentation of congested/saturated lines Demands raised by State Governments/Central Ministries/Public representatives, Railway’s operational requirements Socio-economic considerations Overall availability of funds Completion of Railway project/s depends on various factors which include the following: Land acquisition Forest clearance Shifting of infringing utilities <span style="font-family:Ti